Cupertino · Santa Clara · Bay Area

Scofield Drive and Vista Heights Builder's Remedy Projects

Litigated

20739 Scofield Drive and a hillside site near Linda Vista Park, Cupertino, CA 95014

Units proposed
50
Date filed
February 20, 2024
Delay
32 months
Download brief (print to PDF)Cupertino profileUse the data

Two builder's remedy projects in Cupertino have been stalled since the city declared their applications expired in January 2025. In January 2024, in a suit by YIMBY Law and the California Housing Defense Fund, Santa Clara County Superior Court Judge Mary Arand ruled that developers who filed affordable housing projects after Cupertino missed its housing element deadline could use the builder's remedy until the state approved the city's housing element. Preliminary applications for the two projects followed on February 20 and 21, 2024: one at 20739 Scofield Drive, replacing a single-family home on a corner lot of about 0.32 acres, and one on a hillside near Linda Vista Park that YIMBY Law calls Vista Heights. San Jose Spotlight has described them as 20 condominiums and 33 homes; HCD's notice of violation describes them as a combined 50 units, 10 of them deed-restricted affordable, and the figures above use HCD's count. Residents protested the Scofield Drive proposal at a City Council meeting in July 2024, and neighbors raised fire risk at the hillside site. The applicants filed full applications on August 16 and 19, 2024, and HCD found the city's housing element in substantial compliance on September 4, 2024. The city found the applications incomplete on September 13 and 16, 2024, and on January 9 and 10, 2025 told the applicants that the Permit Streamlining Act allows only one 90-day period to complete an application, so the applications and their vested rights had expired. On April 8, 2025, YIMBY Law, the California Housing Defense Fund and the two applicants filed two petitions in Santa Clara County Superior Court asking that the city be ordered to process the projects. On July 16, 2025, HCD issued a notice of violation saying the 90-day period resets after each incompleteness determination and that the city must honor the projects' vested rights, including builder's remedy status. The city answered in August 2025, defending what it called the plain meaning of the statute. On January 29, 2026, in a separate case brought by the Town of Los Gatos, Judge Helen E. Williams of the same court rejected the single-window reading. No ruling in the Cupertino cases has been reported as of October 2026.

Talk to this project

Ask a question to begin.

Press Enter to send · Switch personas to start a new conversation

Upcoming decision
Petitions over expired applications · Santa Clara County Superior Court
Date not yet set
Builder's remedy applicationApplication completeness dispute

YIMBY Law and the California Housing Defense Fund sued in April 2025 after the city declared two builder's remedy applications expired. HCD issued a notice of violation in July 2025, and the Los Gatos ruling in January 2026 rejected the same legal theory. No Cupertino ruling reported.

Timeline

January 8, 2024Judge Opens Cupertino to Builder's Remedy Projects

In a suit by YIMBY Law and the California Housing Defense Fund, Judge Mary Arand rules that developers who filed affordable housing projects after the city missed its housing element deadline may use the builder's remedy until the state approves the element.

San Jose Spotlight
February 20, 2024Builder's Remedy Preliminary Applications Filed

The two projects file preliminary applications on Feb. 20 and 21, invoking the builder's remedy because the city lacks a compliant housing element.

HCD
July 30, 2024Residents Protest Scofield Drive Plan

San Jose Spotlight reports that more than a dozen residents raised traffic and safety concerns near Faria Elementary School at a City Council meeting earlier in the month. The plan then called for 23 homes.

San Jose Spotlight
August 16, 2024Full Applications Filed

Filed Aug. 16 and 19, within the six months that keep the preliminary applications' vested rights.

HCD
September 13, 2024City Finds Both Applications Incomplete

The incompleteness determinations are dated Sept. 13 and 16, 2024.

HCD
January 9, 2025City Declares Applications Expired

On Jan. 9 and 10, the city tells the applicants that the Permit Streamlining Act allows a single 90-day period to complete an application, so the applications and their vested rights have expired.

HCD
April 8, 2025Housing Groups and Developers Sue Cupertino

YIMBY Law, the California Housing Defense Fund and the two applicants file two petitions in Santa Clara County Superior Court.

San Jose Spotlight
July 16, 2025HCD Issues Notice of Violation

HCD says the 90-day period resets after each incompleteness determination and tells the city to honor the projects' vested rights. The city defends its reading in an August response.

HCD
January 29, 2026Judge Rejects Same Reading in Los Gatos Case

In a suit the Town of Los Gatos brought over two other builder's remedy projects, Judge Helen E. Williams rules that each incompleteness finding opens a new 90-day period.

Los Gatan

Who was involved

Supporting
YIMBY Law
YIMBY Law
Co-petitioner in both suits, filed April 8, 2025

Says Cupertino is trying to stop two builder's remedy projects by claiming an applicant gets only one 90-day window to respond to an incompleteness letter. Executive director Sonja Trauss: "(Cupertino's interpretation) shows that they're desperate to prevent housing in their city."

Kenneth Stahl
Attorney for the Linda Vista Park (Vista Heights) applicant

"There's no reason to read the law that way, except that you want to defeat the builder's remedy." (April 2025)

California Department of Housing and Community Development
State of California
Issued a notice of violation on July 16, 2025 (signed by David Zisser)

"However, the 90-day deadline resets after each incompleteness determination made by the City." The notice told the city to honor the projects' vested rights, including builder's remedy status, and asked for a response by Aug. 15, 2025.

California Housing Defense Fund
California Housing Defense Fund (CalHDF)
Co-petitioner in both suits

Executive director Dylan Casey: "Making sure these builder's remedy projects actually become homes eventually is really important to ensure that state housing policy is functioning as it's intended."

Ryan Patterson
Patterson & O'Neill
Attorney for the Scofield Drive developer

"We've won this argument in court already, and we fully expect to win it again in Cupertino." Also: "(The state's) notice of violation makes it crystal clear: Cupertino is breaking the law and will be held accountable." (August 2025)

Opposing
City of Cupertino
City of Cupertino
Declared both applications and their vested rights expired (Jan. 9 and 10, 2025)

Reads the Permit Streamlining Act to allow a single 90-day period to complete an application after an incompleteness finding. In August 2025 it answered HCD's notice of violation by defending the "plain meaning" of the statute.

Liang Chao
City of Cupertino
Mayor of Cupertino (2025)

"We remain committed to holding everyone to the same objective standards so that more housing can be approved in accordance with our general plan, zoning ordinance and state laws." (April 2025.) After HCD's notice: "Our goal is to ensure all applications meet clear and consistent standards and we treat everyone fairly."

Pandit Prasad
Scofield Drive resident

"Once this gets approved, then there is no control." He said added traffic would endanger his children (July 2024).

Louise Sadaati
Cupertino for All
Cupertino resident and member of the pro-housing group Cupertino for All

"We support housing, but not anything everywhere." Also: "The problems with these two builders' remedies are, as the developers have designed them, they're just not a good fit as submitted."

Deciding
Santa Clara County Superior Court
Court hearing both petitions

No ruling in the Cupertino cases reported as of October 2026. In a separate Los Gatos case, Judge Helen E. Williams ruled on Jan. 29, 2026 that each incompleteness finding opens a new 90-day period.

How it was obstructed

Invoked by City of Cupertino · September 13, 2024

The city found both full applications incomplete on Sept. 13 and 16, 2024, then counted a single 90-day period to cure and declared the applications expired in January 2025. HCD says each incompleteness determination starts a new 90-day period.

Outcome pending
Builder RemedyBuilder's Remedy
Invoked by City of Cupertino · January 9, 2025

With the applications declared expired, the city treats the projects as having lost the builder's remedy rights they vested in February 2024, before the housing element was certified. HCD told the city to honor those rights. Two petitions are pending in Santa Clara County Superior Court.

Outcome pending

Decisions

Each row is a dated action by a deciding body, taken from the minutes, agenda packet, video, or ruling linked in the source column.

DateBodyActionVoteStaff recommendationSource
September 13, 2024Staffdeemed application incomplete
Both full applications were found incomplete, on Sept. 13 and 16, 2024.
—UnknownHCD
April 8, 2025Courtlawsuit filed
Two petitions by YIMBY Law, the California Housing Defense Fund and the applicants, Santa Clara County Superior Court.
—UnknownSan Jose Spotlight

Sources

City of Cupertino, Permit Streamlining Act 90-Day Review, Notice of Violation
California Department of Housing and Community Development2025